Client Case Studies

A success story from a Midwest mall

Problem

  • More than 20 year-old mall with the original absorbsion chillers and steam boilers
  • High energy and maintenance costs

Solution

  • Xencom redesigned the central plant, removed the absobtion chillers and replaced them with two new 900 ton Trane variable drive chillers
  • Converted steam boilers to Hot water
  • Installed new Honeywell XL5000 energy control system with Lon interface to the new Trane chillers

Results

  • Lowered gas electric cost by $230,000 per year
  • Eliminated cost repairs bill for the old chillers
  • Lowered maintenance cost by $100,000 per year