Client Case Studies
A success story from a Midwest mall
|
Problem
- More than 20 year-old mall with the original absorbsion chillers and steam boilers
- High energy and maintenance costs
Solution
- Xencom redesigned the central plant, removed the absobtion chillers and replaced them with two new 900 ton Trane variable drive chillers
- Converted steam boilers to Hot water
- Installed new Honeywell XL5000 energy control system with Lon interface to the new Trane chillers
Results
- Lowered gas electric cost by $230,000 per year
- Eliminated cost repairs bill for the old chillers
- Lowered maintenance cost by $100,000 per year
|
|
 |
 |
|
|
|
 |
|